Wood Group GTS has completed US$2 million worth of major maintenance services for Frame 6B and Frame 5 gas turbines at a U.S. and Costa Rican power station, respectively.

The work included a major inspection and the repair of hot gas path parts: turbine buckets, nozzles, shrouds, transition pieces, crossfire tubes, fuel nozzles, flow sleeves and bearings.

At the U.S. facility, the operating profile of the combined cycle power plant had been changed from base load to peaking duty, serving the reserve power market. As a result, the gas turbine was scheduled to run fewer than 100 hours per year. The projected maintenance cost was significant compared to the revenue likely to be earned by the peaking plant, Wood Group said.

At the Costa Rican facility, there was a greater advantage for the customer to repair their parts rather than replacing them with new components, according to Wood Group.

Wood Group worked with both facilities previously, supplying major maintenance services that have included field services, component repairs, and the supply of Wood Group’s Advanced Parts Manufacture (APM) parts.