Siemens Energy is supplying two gas turbine packages that will eventually operate on 100% hydrogen for the Leipzig Süd district heating power plant in Germany.

The new plant is designed to contribute to the decarbonization of the power supply in two ways: First, the investment will make Stadtwerke Leipzig independent of district heat from the Lippendorf lignite-fired power plant. Secondly, the plant is expected to operate with 30 to 50% green hydrogen only a few years after start of commercial operation. The long-term goal is to operate the facility with 100% hydrogen, the company said. Commissioning is scheduled for the end of 2022.
The new gas power plant with combined heat and power technology will be built on Stadtwerke Leipzig’s existing site on Bornaische Strasse and produce electricity and district heat for the city. It will have an electrical capacity of approximately 125 MW and a thermal capacity of around 163 MW. The plant’s maximum fuel efficiency will be 93%, thanks to the district heat production.
The order from Stadtwerke Leipzig covers the supply of two SGT-800 gas turbines, each with a maximum efficiency of 41%. The turbines are expected to be fired with natural gas, starting in late 2022, and be successively converted to the combustion of ever greater proportions of hydrogen. The long-term goal is to operate the plant with 100% green hydrogen, which can be produced from wind or solar energy by electrolysis. This will permit completely CO2-free and climate-neutral plant operation.
“By investing in a new cutting-edge district heating power plant, we’re not only ensuring that the city of Leipzig will be supplied with electricity and heat in the coming decades,” said Karsten Rogall, Managing Director of Stadtwerke Leipzig. “We are also getting ready to actively pursue decarbonization. The ability to flexibly increase the share of hydrogen in the fuel is an excellent prerequisite for a sustainable and reliable power supply for Leipzig.”
“Our SGT-800 not only achieves the lowest emissions in its class, it is also outstanding with its high fuel flexibility and lower lifecycle costs,” said Karim Amin, executive vice president of Generation at Siemens Energy. “We’re pleased to be working with Stadtwerke Leipzig to further promote the transition towards a new level of decarbonized energy mix in Germany.”
Siemens Energy will provide two SGT-800 gas turbine packages, including two SGen-100A generators. The scope of supply includes a SIESTART battery solution, which ensures that the plant can perform a black start. As a result, the power plant can start up on its own without an external power supply in the unlikely event of a widespread blackout. Siemens Energy will also install and commission the equipment.

STAY CONNECTED



Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

POWER SOURCING GUIDE

The trusted reference and buyer’s guide for 83 years

The original “desktop search engine,” guiding nearly 10,000 users in more than 90 countries it is the primary reference for specifications and details on all the components that go into engine systems.

Visit Now

CONNECT WITH THE TEAM
Becky Schultz Vice President of Content Tel: +1 480 408 9774 E-mail: [email protected]
Julian Buckley Editor Tel: +44 (0) 1892 784088 E-mail: [email protected]
Chad Elmore Managing Editor Tel: +1 262 754 4114 E-mail: [email protected]
Josh Kunz Power Progress Brand Manager Tel: +1 414 379 2672 E-mail: [email protected]
Roberta Prandi Power Progress International Brand Manager Tel: +39 334 6538183 E-mail: [email protected]
Simon Kelly Sales Manager Tel: +44 (0) 1892 786 223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA