Email this page Email Print this page Print Feed Feed

Wärtsilä awarded major O&M contract in Pakistan

Posted on November 12, 2008

Wärtsilä has been awarded an Operations & Maintenance (O&M) agreement to operate and maintain the Attock Gen Ltd power plant, located at the Attock Refinery site near Rawalpindi, Pakistan. The 156 MW power plant, which was supplied and installed by Wärtsilä, will start commercial operations this year.

Wärtsilä currently has O&M agreements in three other power plants in Pakistan, supplying altogether 317 MW of electricity.

The Attock Gen power plant, which is connected to the national grid, utilizes nine Wärtsilä 18V46 type generating sets, with heat recovery boilers on each. Wärtsilä also supplied the plant with an 11.6 MWe steam turbine plant and a 132 kV switchyard.

For more information: WWW.WARTSILA.COM